When to book each stage inspection on a Tarneit build
Slab, frame, lock-up, fixing and PCI: the right moment to inspect each stage and what is lost if you miss it.
In short: Slab the day before the pour, frame after trusses, lock-up before plaster, then fixing and PCI. Each stage hides the last, so timing is everything.
Slab pre-pour
Book for the day before the pour. We check reinforcement, bar chairs, cover, penetrations, vapour barrier and edge beams. Once concrete is poured nothing here can be checked again.
Frame
After the roof trusses are on and before the roof and wrap go on. Straightness, bracing, tie-downs, lintels and window openings are all visible at this point only.
Lock-up (pre-plaster)
After brickwork, windows and roof, before plaster. Flashings, wall wrap, mortar joints, roof space framing and services are checked before they are covered.
Fixing and PCI
Fixing catches waterproofing, tiling and cabinetry before paint. PCI is the final list. Together they close out the defects that appear at handover.
Written by the Owner Inspections team from inspections carried out in Tarneit. Licensed building practitioners, Building & Plumbing Commission registration CDB-U 53425.